September 30, 2014

Lillie Corridor Storage

Marine Biological Laboratory
Policy No. D.1.9

Facilities

Initiated by:Associate Director
Approved by:MBL Director/CEO
Date:June 21, 1990
Revision #:
Distribution:All occupants of the Lillie Building

1.0Policy Statement:
Material and equipment stored in the corridors of the Lillie Building is a safety hazard as well as a violation of the fire code.

2.0Procedure:
Effective October 1, 1990, all materials belonging to specific labs must be removed from the corridors.

2.1The MBL will work to locate suitable areas to relocate current material.
2.2It is the responsibility of the individual lab to move the material.
2.3No new material may be placed in the corridors.

3.0Policy Clarification and Updates:
Policy clarification and updates are available from the Facilities Office.